How to Install a Doughboy Above-Ground Swimming Pool
Things You'll Need
- Shovel
- Patio blocks
- Hose
Instructions
-
Laying the Framework
-
1
Remove the sod where your pool will be placed, and level the ground. Dig out higher areas until they are the same height as the lowest point.
-
2
Assemble the bottom frame, placing a patio block at each seam in the frame where two pieces come together.
-
3
Install the wall by unrolling it in 6- to 10-foot segments and inserting it into the bottom framework.
-
4
Slide the wall joint into place to join the start and end of the wall.
-
5
Slide the verticals into position at each seam in the frame, and top them off with end caps.
-
6
Put the top railings on around the perimeter of the pool and hold them in place by inserting the top caps onto the verticals.
-
7
Create a "cove" around the interior of the pool, by tightly packing dirt around the entire interior in an arc that is approximately 6 inches high, and 9 inches long, or using pre-made cove wedges.
Filling Your Pool
-
8
Place the liner along the surface of the pool, leaving about 2 feet of hangover around all sides of the pool.
-
9
Clip the liner to the pool with binder clips on either side of the verticals.
-
10
Begin filling the pool with a hose until the water level is above the cove.
-
11
Remove three adjacent sections of the top rail.
-
12
Slide the coping over the liner, and the stabilizers over the coping in the exposed sections.
-
13
Replace the removed top railings, and repeat the process for the remainder of the pool, traveling clockwise until the entire liner is secure.
-
14
Finish filling the pool with water.
-
1