How to Build Skateboarding Rails
Things You'll Need
- 2-inch OD schedule 80 steel pipe
- Electric drill
- 3/8-inch drill bit
- 3/16-inch drill bit
- 2 1/2-inch screws
- 1 5/8-inch screws
- Two 2-by-4 pieces of lumber
- One 2-by-6 piece of lumber
- 1/2 inch sheet of plywood
- Band saw
Instructions
-
-
1
Take the skateboard rail materials to a flat, paved surface. Cut the two 2-by-4 pieces of lumber and the 2-by-6 piece to correspond with the length of the steel pipe. Lay one 2-by-4 on its 2-inch side. Place the other 2-by-4 on top and center it to create a T shape.
-
2
Drill the 2 1/2-inch screws through the top of the T shape, going down the length of the wood while spreading the screws out six inches. Lay the 2-by-6 flat on its 6-inch side.
-
3
Flip the T-shaped 2-by-4s upside down and center them on top of the 2-by-6. Drill screws through the top of the horizontal 2-by-4, going around the vertical 2-by-4, to attach it to the 2-by-6. Spread the screws out six inches.
-
4
Cut two pieces of the half-inch-thick plywood to have a width of seven inches and a length that corresponds with the 2-by-4s and the 2-by-6 piece. Lay a piece of the seven-inch-wide plywood against both sides of the 2-by-4 and 2-by-6 structure to create a pyramid-shaped design.
-
5
Drill the 1 5/8-inch screws through the top and bottom of the plywood to attach the pieces to the 2-by-4s and 2-by-6. Space out the screws six inches going down the length of the structure.
-
6
Measure two inches away from both ends of the steel pipe moving towards the middle. Drill a 3/8-inch hole through the top of the pipe at both two-inch measurements. Drill a 3/16-inch hole directly under both of the 3/8-inch holes.
-
7
Lay the rail on the top of the pyramid-shaped 2-by-4 and 2-by-6 structure with the 3/8-inch holes facing up. Drill a 1 5/8-inch screw through the two 3/16-inch holes to attach the steel pipe to the vertical 2-by-4.
-
8
Drill a 3/8-inch hole through the top of the pipe for every four inches of space between the two original holes. Drill a 3/16-inch hole under every 3/8-inch hole. Drill a 1 5/8-inch screw through every 3/16-inch hole to stabilize the pipe to the vertical 2-by-4.
-